The PDF recaps on the demos the trainer did two weeks ago.

The project is a simple TODO Application, the specification can be found here

You are going to create two projects, a Kanban Team Managed project and Kanban Company Managed project. The purpose of the exercise is to simply recognise the difference between the project types.

...

  1. Navigate to https://celestial.atlassian.net/jira/ and log in using your team IDs

  2. Select Kanban

  3. On the next page select team-managed project

  4. In the Name field enter the project name according to the naming convention above - as you are typing you may see project names coming up, do not select them. You are using a single Jira instance, and it retains the names of previously created projects. Let Jira enter the value into the key field, do not edit this field. Also set the access level if it is being shown

  5. Once the project is created you will see an empty board

  6. Turn on the features Backlog and Issues Navigator

  7. You are now ready to add your issues

  8. Decide on 2 stories you want to work with, add them into your project using the “Create Issue” window. In the Labels field create a new label todoapp but prefix it with your teams ID e.g. 01-todoapp. Populate the other fields as necessary. The stories can be found here

  9. An issue can be created by selecting the Create button

  10. Now populate the fields as necessary (no real

  11. Move the issues from the backlog to the board

  12. Image RemovedImage Added

    Move the issues around the board either by dragging them between the board columns

  13. Move the issues around the board by changing the status of the issue (click on the issue the see the following window)

...

  1. Navigate to https://celestial.atlassian.net/jira/ and log in using your team IDs

  2. Select Scrum

  3. Select Company managed

  4. In the Name field enter the project name according to the naming convention above - as you are typing you may see project names coming up, do not select them. You are using a single Jira instance, and it retains the names of previously created projects. Let Jira enter the value into the key field, do not edit this field. Make sure the two checkboxes shown here are deselected. Once you’ve entered the project name the Create Project button will be highlighted, select it

  5. Once the project is created you will see an empty board.

  6. If the backlog is not showing turn the feature on

  7. You are now ready to add your stories

  8. Decide on 2 stories you want to work with, add them into your project using the “Create Issue” window. In the Labels field create a new label todoapp but prefix it with your teams ID e.g. 01-todoapp. Populate the other fields as necessary. The stories can be found here

  9. An issue can be created by selecting the Create button

  10. Now populate the fields as necessary

  11. Move the issues from the backlog to the board

    1. Image RemovedImage Added
  12. Move the issues around the board either by dragging them between the board columns